Bid Help

I have an Electrical Bid that needs to be brought up to code.The electrician i found wants 5500 total for the job(No Discount).How do you guy make a few bucks for going back and forth to the property and your time taking photos etc, when subbing out work to others?Do you tack on a percentage or?
UnitedFieldInspections is offline  
Sponsored Links
Advertisement
 
post #2 of 12 (permalink) Old 03-11-2014, 10:00 PM
Senior Member
 
Join Date: Apr 2012
Location: ohio
Posts: 568
Thanks: 137
Thanked 307 Times in 177 Posts
20% profit margin
hammerhead is offline  
post #3 of 12 (permalink) Old 03-11-2014, 10:01 PM
Senior Member
 
Join Date: Sep 2012
Posts: 588
Thanks: 192
Thanked 255 Times in 114 Posts
Its actually easy, take the subs price and ad whatever you want to make on it. If the client says no then just have them get somebody else.
brm1109 is offline  
The Following 3 Users Say Thank You to brm1109 For This Useful Post:
Field Audit Services LLC (03-13-2014), mtmtnman (03-11-2014), STARBABY (03-11-2014)
Sponsored Links
Advertisement
 
post #4 of 12 (permalink) Old 03-12-2014, 03:20 PM
Member
 
Join Date: Feb 2014
Posts: 38
Thanks: 11
Thanked 13 Times in 8 Posts
That's right, don't do it unless you make at least 20%. Make as much as the Field Service Company is you are working for. After all, they aren't doing the work, taking the photo's, paying the contractor immediately and waiting for their money like you are. Also, it's all on your head. If they aren't happy with the job, off it comes.
honyocktrapper is offline  
post #5 of 12 (permalink) Old 03-12-2014, 04:09 PM
Member
 
Join Date: May 2012
Posts: 80
Thanks: 18
Thanked 28 Times in 18 Posts
20% usually. Keep in mind, that $5500 that was in your bank account scot free is now taking the form of a receivable from that company. So for me it comes down to how much confidence and trust I have in that company.
ADP LLC is offline  
post #6 of 12 (permalink) Old 03-12-2014, 06:47 PM
Member
 
Join Date: Feb 2014
Posts: 38
Thanks: 11
Thanked 13 Times in 8 Posts
20 %. but we never get the bids. then your ele contractor will refuse to bid for free after 2 or 3 failed bids. we ended up going aroundandaroundandaround.
honyocktrapper is offline  
post #7 of 12 (permalink) Old 03-12-2014, 09:45 PM
Super Moderator
 
GTX63's Avatar
 
Join Date: Apr 2012
Location: Your House Soon...Soon
Posts: 3,186
Thanks: 676
Thanked 2,249 Times in 1,094 Posts
So at $5500 you might be at the high end of the pricing chart for that job already, depending on the electrical sub you are using. So tacking on 20% your at $6600, and you think "Man, how is the bank going to go for this? I'm wasting my time." But wait, your rep takes your bid and puts another 30-40% on top of that. Your thinking that only the government pays $600 for a toilet seat? This is crazy talk.

So, about 6 weeks later, at $9240, your client gets the approval and sends over the work order. You don't know what they are getting; your just hoping you can cover the expenses until your are reimbursed and that they don't hit you with their discount. By now the electrician may have blown you off and is either busy or won't return your calls. You either find another guy for similar money or plan your days around when he may or may not be there so you can take enough of the required photos to avoid the "email of death".

No, they aren't all like that. But it's hard on the little mom and pops who have to risk most of their working capital to hourly wage clerics who may or may not decide the job is worth paying the bid price for.
GTX63 is offline  
The Following 2 Users Say Thank You to GTX63 For This Useful Post:
Racerx (03-14-2014), UnitedFieldInspections (03-13-2014)
post #8 of 12 (permalink) Old 03-13-2014, 02:27 AM Thread Starter
Senior Member
 
UnitedFieldInspections's Avatar
 
Join Date: Dec 2012
Location: New York & New Jersey
Posts: 350
Thanks: 163
Thanked 137 Times in 95 Posts
Quote:
Originally Posted by GTX63 View Post
So at $5500 you might be at the high end of the pricing chart for that job already, depending on the electrical sub you are using. So tacking on 20% your at $6600, and you think "Man, how is the bank going to go for this? I'm wasting my time." But wait, your rep takes your bid and puts another 30-40% on top of that. Your thinking that only the government pays $600 for a toilet seat? This is crazy talk.

So, about 6 weeks later, at $9240, your client gets the approval and sends over the work order. You don't know what they are getting; your just hoping you can cover the expenses until your are reimbursed and that they don't hit you with their discount. By now the electrician may have blown you off and is either busy or won't return your calls. You either find another guy for similar money or plan your days around when he may or may not be there so you can take enough of the required photos to avoid the "email of death".

No, they aren't all like that. But it's hard on the little mom and pops who have to risk most of their working capital to hourly wage clerics who may or may not decide the job is worth paying the bid price for.


I agree,The part that worries me the most is laying out my money and praying to get paid
UnitedFieldInspections is offline  
post #9 of 12 (permalink) Old 03-13-2014, 07:19 AM
Super Moderator
 
GTX63's Avatar
 
Join Date: Apr 2012
Location: Your House Soon...Soon
Posts: 3,186
Thanks: 676
Thanked 2,249 Times in 1,094 Posts


Friday, March 12th, 9:56 p.m. UTC + 4

Please note and address the following items to us within 8 hours, our time, of our sending of this compliance shortfall.

Improper spacing between saddle clamps along lower level floor joist.

Insufficient photos of junction box connections; also conduit should not be entering into the side but the front and rear only.

Please return and submit photos of subfloor wiring showing 12/2 grade printed on sleeve

No mpg audio formatted attachments of kitchen range hood in service found.

Current photos do not justify amount of cabling on invoice. Please return and verify or adjust billing .93 per unwound ft.

Submit time and date stamped confirmation of the following-
closet lights are on same circuit as bedroom
bathroom vent fans are on separate circuit for/from light/fan
All GFCI outlets are on branch and not line circuits
Please relocate subpanel for garage onto rear or south exterior wall of house with proper all weather cover and proprietary lock
Circuit tester being used and shown lit in each and all wall outlets (one at a time is acceptable)
Confirm photo exf data matches or is prior to final inspection walk thru and signature date on card

A billing accommodation of up to 6% per line item may be included to this order.

Submit all of the above with explanations of who you are with your vendor confirmation addendums, the work order property address with mortgager information and form Tenn 11AR to our processing center located at 666 Fortunemaker Way, Augua Priente, Mexico, att: Las Americanos Pila
GTX63 is offline  
post #10 of 12 (permalink) Old 03-13-2014, 08:22 AM
Contractor
 
JFMURFY's Avatar
 
Join Date: Sep 2012
Location: CT
Posts: 486
Thanks: 81
Thanked 151 Times in 79 Posts
Project Management add $100 per visit anticipated. Add 25% Profit & O/H
JFMURFY is offline  
Reply

Quick Reply
Message:
Options

Register Now



In order to be able to post messages on the REO Property Preservation Forum forums, you must first register.
Please enter your desired user name, your email address and other required details in the form below.

User Name:
Password
Please enter a password for your user account. Note that passwords are case-sensitive.

Password:


Confirm Password:
Email Address
Please enter a valid email address for yourself.

Email Address:
OR

Log-in










Thread Tools
Show Printable Version Show Printable Version
Email this Page Email this Page
Display Modes
Linear Mode Linear Mode



Posting Rules  
You may post new threads
You may post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

 
For the best viewing experience please update your browser to Google Chrome