FAS sending contactors to inspect after work is perform

I have been getting e-mails from FAS stating Contractor B was sent to check on work completed. FAS is paying contactor B by debit first contactor.

The amount I was charge for them to rework cleaning,debris was very excessive (1 job payed $450 was debited $125). Work contractor B did looked staged. I have filled a complaint with FAS, got a responce that do to the large amount of debit it will take 30days to review.

I have already reduced my workflow with them. With this and the new cost plus program do not see must reason to keep doing work for them.

I started in with FAS in 2000, how they have fallen!!!!!
STARBABY is offline  
Sponsored Links
Advertisement
 
post #2 of 23 (permalink) Old 12-31-2011, 10:56 PM
FremontREO
Guest
 
Posts: n/a
Yep that is how the game is played. Now ask for a copy of contractor B's invoice, pics and completion notes.
See how far that will get ya...

BTW...go to introductions section and introduce yourself. Its customary. Welcome to CT.
post #3 of 23 (permalink) Old 12-31-2011, 11:28 PM
STARBABY
Guest
 
Posts: n/a
It does seem fas is playing alot more games today. Would ask for copy of contractor B`s invoice if I knew who to ask. In the e-mails with the debits fas only gives you a e-mail address and the responces from them look like mass email responces.

thanks will check out introduction section
Sponsored Links
Advertisement
 
post #4 of 23 (permalink) Old 01-01-2012, 08:58 AM
Senior Member
 
thanohano44's Avatar
 
Join Date: Aug 2012
Posts: 2,016
Thanks: 1,397
Thanked 289 Times in 168 Posts
Quote:
Originally Posted by STARBABY
It does seem fas is playing alot more games today. Would ask for copy of contractor B`s invoice if I knew who to ask. In the e-mails with the debits fas only gives you a e-mail address and the responces from them look like mass email responces.

thanks will check out introduction section
Ask Andre Harris
thanohano44 is offline  
post #5 of 23 (permalink) Old 01-02-2012, 06:03 AM
Super Moderator
 
GTX63's Avatar
 
Join Date: Apr 2012
Location: Your House Soon...Soon
Posts: 3,186
Thanks: 676
Thanked 2,249 Times in 1,094 Posts
Quote:
Originally Posted by STARBABY

I started in with FAS in 2000, how they have fallen!!!!!
How many people from FAS that were there in 2000 remain today?

Answer: The ones that deposit the checks.
GTX63 is offline  
post #6 of 23 (permalink) Old 01-02-2012, 06:05 AM
Super Moderator
 
GTX63's Avatar
 
Join Date: Apr 2012
Location: Your House Soon...Soon
Posts: 3,186
Thanks: 676
Thanked 2,249 Times in 1,094 Posts
They don't normally send an REO sub to do a QC. It is normally an inspector. Then they send you a follow up list of deficiencies to correct "or else!".
GTX63 is offline  
post #7 of 23 (permalink) Old 01-02-2012, 10:36 AM
Senior Member
 
Join Date: Apr 2012
Posts: 2,403
Thanks: 1,518
Thanked 533 Times in 287 Posts
Quote:
Originally Posted by GTX63
They don't normally send an REO sub to do a QC. It is normally an inspector. Then they send you a follow up list of deficiencies to correct "or else!".
Sending another contractor is very common with any of these companies...........................
mtmtnman is offline  
post #8 of 23 (permalink) Old 01-02-2012, 11:50 AM
scutrman
Guest
 
Posts: n/a
This has happened to me too. I no longer take work in the area where a specific vendor B inspects because they always find (bring with them) debris. It is my understanding they are not paid for this, only the promise of more work to offset the inspections.
post #9 of 23 (permalink) Old 01-02-2012, 12:21 PM
Lawn Mower Man
Guest
 
Posts: n/a
Lost count of the number of cheap inspections we have done following the work the other contractors.

Gotta love the ones who leave "US" $100.00s in hazards and sub par clean outs that we get our full janitorial rate to bill rather then a simple routine cleaning!!!

Nice way to turn a weak "fill work" day into profit for the week
post #10 of 23 (permalink) Old 01-02-2012, 08:46 PM
STARBABY
Guest
 
Posts: n/a
Lost count of the number of cheap inspections we have done following the work the other contractors.

Gotta love the ones who leave "US" $100.00s in hazards and sub par clean outs that we get our full janitorial rate to bill rather then a simple routine cleaning!!!

Nice way to turn a weak "fill work" day into profit for the week


I have seen also seen sub par clean outs,missed hand rail ect, but I see them due to being asigned the maid services on the property.

I do not believe there was any problems with my property and I`m getting scamed by another vendor.
Reply

Quick Reply
Message:
Options

Register Now



In order to be able to post messages on the REO Property Preservation Forum forums, you must first register.
Please enter your desired user name, your email address and other required details in the form below.

User Name:
Password
Please enter a password for your user account. Note that passwords are case-sensitive.

Password:


Confirm Password:
Email Address
Please enter a valid email address for yourself.

Email Address:
OR

Log-in










Thread Tools
Show Printable Version Show Printable Version
Email this Page Email this Page
Display Modes
Linear Mode Linear Mode



Posting Rules  
You may post new threads
You may post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

 
For the best viewing experience please update your browser to Google Chrome